COURTHOUSE NEWS: Dam it: 10th Circuit lets Denver Water complete Gross Reservoir expansion
Fetched 2026-09-17 08:03 from mavensnotebook.com
Reading Summary (AI-generated)
Reading Summary: 10th Circuit Clears Gross Reservoir Expansion
Key Facts
- The 10th Circuit vacated a permanent injunction blocking Denver Water from filling the expanded Gross Reservoir, remanding with instructions to enter judgment against the environmental plaintiffs
- The $600 million Gross Dam expansion added 131 feet to the dam’s height and enables storage of an additional 77,000 acre-feet of water; physical construction was completed in July 2026
- Denver Water projected needing 18,000 acre-feet per year of new firm yield to serve 1.5 million people in the Denver region
- The project diverts water from the Colorado River (Western Slope) for storage at Gross Reservoir (Eastern Slope), allowing year-round operation of the Moffat Water Treatment Plant
- The permit process spanned 14 years (applied 2003, granted 2017); litigation began in 2018 and ran through 2026
Who Is Affected
- Denver Water ratepayers and the ~1.5 million people served by the northern system (currently only 10% of customers)
- U.S. Army Corps of Engineers and Department of the Interior, whose environmental reviews were contested
- Save the Colorado and allied environmental groups, who lost after an eight-year legal fight
- Colorado River basin ecosystems on the Western Slope subject to additional diversions
- Wetland and riparian habitats around Gross Reservoir (tree clearing was blocked under the injunction)
Policy/Legal Angle
- Clean Water Act (Section 404 wetlands permit) and National Environmental Policy Act (NEPA) — district court found reviews inadequate; 10th Circuit reversed, applying strong deference to agency technical judgment
- Core legal question: whether the Army Corps acted arbitrarily and capriciously by screening out alternatives that did not expand Gross Reservoir — the 10th Circuit said no
- Judge Tymkovich’s opinion reinforces the Chevron-adjacent deference standard for agency scientific and technical determinations, notable in the post-Loper Bright regulatory environment
- Case history: dismissed 2021 → revived by 10th Circuit 2022 → bench trial 2024 → injunction partially modified on appeal → fully vacated 2026
Blog Angles
- West Slope vs. East Slope water transfers: With the Colorado River already over-allocated, what does adding a significant new trans-mountain diversion mean for downstream water users, compact obligations, and ongoing drought negotiations? How does this project interact with Colorado’s 2023 Drought Response Operations Agreement?
- The deference question post-Loper Bright: The 10th Circuit leaned heavily on agency deference for technical NEPA/CWA determinations — does this ruling signal how Western federal courts will handle environmental challenges to water infrastructure permits in an era of Supreme Court skepticism toward agency deference?
- Infrastructure timing vs. litigation risk: Denver Water spent $600 million and completed construction before final legal resolution — what does this case reveal about how utilities and agencies strategically sequence construction and litigation to make injunctions moot, and should courts weigh that dynamic differently?
Full Text
COURTHOUSE NEWS: Dam it: 10th Circuit lets Denver Water complete Gross Reservoir expansion
Denver Water planned to complete construction on Colorado’s largest dam by next year until environmental groups secured an injunction in 2024 blocking the utility from filling the expanded reservoir.
By Amanda Pampuro, Courthouse News Service
The 10th Circuit cleared the way for Denver Water to complete the Gross Dam and fill the expanded reservoir by vacating a lower court’s permanent injunction on Tuesday, bringing the end in sight for Colorado’s largest dam project more than two decades after it was initially planned.
“The touchstone for judicial review of agency action is deference, and nowhere is deference more appropriate than when an agency exercises its expertise to make technical and scientific judgments,” U.S. Circuit Judge Timothy Tymkovich wrote in a 37-page opinion. “The Corps’ three determinations — which the district court found arbitrary and capricious — fall easily within that zone of discretion, and none of those determinations were arbitrary or capricious.”
Denver Water began designing the Moffat Collection System Project and Gross Dam expansion 24 years ago in anticipation of future water shortages. The utility initially applied for a wetlands permit from the U.S. Army Corps of Engineers in 2003, which was granted more than a decade later in 2017.
Claiming the federal government issued permits without adequate environmental review, nonprofit Save the Colorado joined several other environmental groups in suing the Army Corps and the Department of the Interior in December 2018.
Senior U.S. District Judge Christine Arguello initially granted the government’s motion to dismiss in 2021, citing lack of subject-matter jurisdiction. The environmental groups appealed, and the 10th Circuit revived the case in 2022 just as dam construction began.
Following a 2024 bench trial, the George W. Bush appointee found the government’s environmental review inadequate under the Clean Water Act and National Environmental Policy Act. After initially enjoining further construction, Arguello allowed the utility to complete the structure while it appealed but prevented the dam from being filled to its full potential. The 10th Circuit heard argument from both Denver Water and the Army Corps of Engineers in July.
Engineers completed the $600 million dam expansion in July, adding 131 feet to the dam’s height, enabling it to hold an additional 77,000 acre-feet of water . Under the lower court’s order, Denver Water was barred from clearing trees around the reservoir and using the newly added expansion.
In its permit application, Denver Water anticipated needing to secure an additional 18,000 acre-feet per year of new firm yield to provide for 1.5 million people. In addition to needing more water, Denver also sought to make its overall system more efficient while pulling water from separate sources and storing it around the state.
Once complete, the project will allow Denver Water to divert water from the Colorado River on the Western Slope of the Rocky Mountains and store it in the Gross Reservoir on the Eastern Slope. This allows the utility to shore up shortfalls in its northern system, which currently only reaches 10% of customers. The project will also allow the Moffat Water Treatment Plant to run year-round and through anticipated droughts.
In Tuesday’s opinion, the 10th Circuit found the government wasn’t wrong to tailor the project toward achieving both of Denver Water’s goals — to increase water and reduce reliance on the southern system. The panel also found it reasonable that the federal agency ruled out projects that didn’t require expanding the Gross Reservoir and Dam.
“The Corps did not act arbitrarily or otherwise contrary to law by screening out proposed alternatives that could not increase water supply to the Moffat Treatment Plant,” Bush-appointed Tymkovich wrote.
In vacating the permanent injunction, the court ordered the case be remanded to the lower court “with instruction to enter judgment against the plaintiff.”
Todd Hartman, a spokesperson for Denver Water celebrated the decision.
“With this decision, Denver Water can move forward with completion of construction, site preparation and eventual filling of the expanded reservoir,” Hartman said over email. “An expanded Gross Reservoir is vital to the future of the Denver region, giving Denver Water far greater ability to flexibly manage constrained water supplies amid the growing risks of catastrophic wildfire and weather extremes that accompany the challenges of drought and climate change already upon us.”
Fellow Bush appointee Chief U.S. Circuit Judge Jerome Holmes joined the opinion with Barack Obama-appointed U.S. Circuit Judge Nancy Moritz.
A U.S. Department of Justice spokesperson declined to comment, as did attorney William Eubanks, who represented the environmental groups.